The Space Network Ground Segment Sustainment effort successfully completed its Key Decision Point - B review at NASA allowing the project to proceed into Phase B of its lifecycle, the Mission Definition Phase. During this next phase, lasting approximately eight months, the network will hold its Preliminary Design Review and complete additional project planning.
Approval to move forward was granted during a recent Agency Project Management Council meeting at NASA Headquarters, Washington, chaired by William Gerstenmaier, associate administrator for the Human Exploration and Operations Mission Directorate (HEOMD).
"Completing Key Decision Point - B (KDP-B) is a major achievement and reflects the fact that we have a very capable team in place," said Roger Clason, Space Network Ground Segment Sustainment (SGSS) Project Manager at NASA's Goddard Space Flight Center, Greenbelt, Md.. "It was gratifying to see, at all levels of management, recognition of SGSS's importance to the future of NASA's space communications capabilities."